[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149580":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149580,802,2,"多选题","当基坑底有承压水时，应进行坑底突涌验算，必要时可采取（ ）保证坑底土层稳定。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","截水",false,{"key":16,"text":17,"correct":18},"B","水平封底隔渗",true,{"key":20,"text":21,"correct":14},"C","设置集水井",{"key":23,"text":24,"correct":18},"D","钻孔减压",{"key":26,"text":27,"correct":14},"E","回灌","BD","2020教材P115 \u002F 2019教材P116 （4）当基坑底为隔水层且层底作用有承压水时，应进行坑底突涌验算，必要时可采用水平封底隔渗或钻孔减压措施，保证坑底土层稳定。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]