[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149568":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149568,802,2,"多选题","放坡基坑施工中，常用的护坡措施有（ ）等。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","挂网喷浆或混凝土",true,{"key":16,"text":17,"correct":18},"B","型钢支撑",false,{"key":20,"text":21,"correct":14},"C","锚杆喷射混凝土",{"key":23,"text":24,"correct":14},"D","水泥抹面",{"key":26,"text":27,"correct":14},"E","叠放砂包或土袋","ACDE","2020教材P127 \u002F 2019教材P128 放坡开挖时应及时作好坡脚、坡面的保护措施。常用的保护措施有： 1）叠放砂包或土袋：用草袋、纤维袋或土工织物袋装砂（或土），沿坡脚叠放一层或数层，沿坡面叠放一层； 2）水泥砂浆或细石混凝土抹面； 3）挂网喷浆或混凝土； 4）其他措施：包括锚杆喷射混凝土护面、塑料膜或土工织物覆盖坡面等。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]