[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149567":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149567,802,2,"多选题","放坡基坑施工中，当边坡有失稳迹象时，应及时采取（ ）或其他有效措施。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","削坡",true,{"key":16,"text":17,"correct":14},"B","坡顶卸荷",{"key":19,"text":20,"correct":14},"C","坡脚压载",{"key":22,"text":23,"correct":24},"D","断续开挖",false,{"key":26,"text":27,"correct":24},"E","加快施工进度","ABC","2020教材P127 \u002F 2019教材P128 基坑边坡稳定控制措施：6）在整个基坑开挖和地下工程施工期间，应严密监测坡顶位移，随时分析监测数据。当边坡有失稳迹象时，应及时采取削坡、坡顶卸荷、坡脚压载或其他有效措施。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]