[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149563":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149563,802,2,"多选题","在明挖基坑开挖过程中，经监测发现支撑立柱发生缓慢隆起，过大的坑底隆起按基坑变形分析，其可能原因是（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","基地扰动",false,{"key":16,"text":17,"correct":14},"B","地下承压水水头变化",{"key":19,"text":20,"correct":14},"C","土方开挖过快，造成坑底强烈卸荷",{"key":22,"text":23,"correct":24},"D","围护结构入土深度不足，造成基底隆起",true,{"key":26,"text":27,"correct":24},"E","基坑底不透水土层由于其自重不能够承受不透水土层下承压水水头压力","DE","2020教材P132 \u002F 2019教材P133 4.过大的坑底隆起可能是两种原因造成的：（1）基坑底不透水土层由于其自重不能够承受不透水土层下承压水水头压力而产生突然性的隆起；（2）基坑由于围护结构插入坑底土层深度不足而产生坑内土体隆起破坏。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]