[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149525":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149525,802,2,"多选题","斜拉桥的零号段是梁的起始段，一般都在支架和托架上浇筑，浇筑前应消除支架的()。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","弹性变形",true,{"key":16,"text":17,"correct":14},"B","非弹性变形",{"key":19,"text":20,"correct":14},"C","温度变形",{"key":22,"text":23,"correct":14},"D","支承变形",{"key":25,"text":26,"correct":27},"E","压缩变形",false,"ABCD","2020教材P89 \u002F 2019教材P90 1）混凝土主梁施工方法第一点：斜拉桥的零号段是梁的起始段，一般都在支架和托架上浇筑。支架和托架的变形将直接影响主梁的施工质量。在零号段浇筑前，应消除支架的温度变形、弹性变形、非弹性变形和支承变形。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]