[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149521":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149521,802,2,"多选题","钢-混凝土组合梁混凝土桥面应全断面连续浇筑，以下浇筑顺序正确的是()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","顺桥向自跨中向支点处浇筑",true,{"key":16,"text":17,"correct":14},"B","顺桥向由一端开始浇筑",{"key":19,"text":20,"correct":21},"C","顺桥向自两端向跨中浇筑",false,{"key":23,"text":24,"correct":14},"D","横桥向由中间向两侧浇筑",{"key":26,"text":27,"correct":21},"E","横桥向由两侧向中间浇筑","ABD","2020教材P84 \u002F 2019教材P85 5）混凝土桥面结构应全断面连续浇筑，浇筑顺序：顺桥向应自跨中开始向支点处交汇，或由一端开始浇筑；横桥向应先由中间开始向两侧扩展。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]