[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149520":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149520,802,2,"多选题","钢—混凝土组合梁施工，浇筑混凝土前应对钢主梁的()进行检查验收。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","焊接质量",false,{"key":16,"text":17,"correct":18},"B","安装位置",true,{"key":20,"text":21,"correct":14},"C","几何尺寸",{"key":23,"text":24,"correct":18},"D","纵横向连接",{"key":26,"text":27,"correct":18},"E","施工支架","BDE","2020教材P84 \u002F 2019教材P85 3）混凝土浇筑前，应对钢主梁的安装位置、高程、纵横向连接及施工支架进行检查验收，各项均应达到设计要求或施工方案要求。钢梁顶面传剪器焊接经检验合格后，方可浇筑混凝土。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]