[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149518":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149518,802,2,"多选题","斜拉桥钢主梁施工时，应连续观测钢梁的温度变形，以便采取正确的合龙措施，以下措施正确的是()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","确定合龙时间",false,{"key":16,"text":17,"correct":18},"B","确定合龙程序",true,{"key":20,"text":21,"correct":14},"C","调节合龙口长度",{"key":23,"text":24,"correct":18},"D","满足钢梁安装就位时高强螺栓定位所需的时间",{"key":26,"text":27,"correct":18},"E","确定合龙温度","BDE","2020\u002F2019教材P90 ③应进行钢梁的连日温度变形观测对照，确定适宜的合龙温度及实施程序，并应满足钢梁安装就位时高强螺栓定位所需的时间。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]