[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149516":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149516,802,2,"多选题","现浇混凝土斜拉桥主梁施工时，应采取措施防止合龙梁段施工出现的裂缝，以下措施正确的是()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","不间断观测合龙前数日昼夜环境温度变化与合龙高程及合龙口长度变化的关系",true,{"key":16,"text":17,"correct":14},"B","可视情况进行适当压重",{"key":19,"text":20,"correct":21},"C","预应力索张拉后禁止施工荷载的不平衡变化",false,{"key":23,"text":24,"correct":14},"D","确定适宜的合龙时间和合龙程序",{"key":26,"text":27,"correct":14},"E","采取临时措施调节合龙口的应力和合龙口长度","ABDE","2020\u002F2019教材P90 2）混凝土主梁施工方法第六点：为防止合龙梁段施工出现的裂缝，在梁上下底板或两肋的端部预埋临时连接钢构件，或设置临时纵向预应力索，或用千斤顶调节合龙口的应力和合龙口长度，并应不间断地观测合龙前数日的昼夜环境温度场变化与合龙高程及合龙口长度变化的关系，确定适宜的合龙时间和合龙程序。合龙两端的高程在设计允许范围之内，可视情况进行适当压重。合龙浇筑后至预应力索张拉前应禁止施工荷载的超平衡变化。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]