[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149509":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149509,802,2,"多选题","钢梁安装前检查的内容包括()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","钢梁的焊接质量",false,{"key":16,"text":17,"correct":18},"B","对临时支架、支承、吊机等临时结构和钢梁结构本身在不同受力状态下的强度、刚度及稳定性进行验算",true,{"key":20,"text":21,"correct":14},"C","钢梁的几何尺寸",{"key":23,"text":24,"correct":18},"D","对桥台、墩顶面高程、中线及各孔跨径进行复测",{"key":26,"text":27,"correct":18},"E","按照构件明细表核对进场的构件零件，查验产品出厂合格证及材料的质量证明书","BDE","2020\u002F2019教材P82 二）安装前检查(1)钢梁安装前应对临时支架、支承、吊机等临时结构和钢梁结构本身在不同受力状态下的强度、刚度及稳定性进行验算。(2)应对桥台、墩顶顶面高程、中线及各孔跨径进行复测，误差在允许偏差范围内方可安装。(3)应按照构件明细表，核对进场的构件、零件，查验产品出厂合格证及钢材的质量证明书。(4)对杆件进行全面质量检查，对装运过程中产生缺陷和变形的杆件，应进行矫正。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]