[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149508":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149508,802,2,"多选题","钢梁制作基本要求中，以下表述正确的有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","钢梁制造焊接环境相对湿度不宜高于80%",true,{"key":16,"text":17,"correct":14},"B","主要杆件应在组装后24h内焊接",{"key":19,"text":20,"correct":21},"C","钢梁在现场必须进行试拼装，并应按设计和有关规范的要求验收",false,{"key":23,"text":24,"correct":21},"D","钢梁制作的工艺中，不需要对构件变形矫正",{"key":26,"text":27,"correct":21},"E","钢梁出厂后，安装企业应对钢梁质量和应交付的文件进行验收，确认合格","AB","2020\u002F2019教材P82 2）钢梁制作基本要求1)钢梁制作的工艺流程：包括钢材矫正，放样画线，加工切割，再矫正、制孔，边缘加工、组装、焊接，构件变形矫正，摩擦面加工，试拼装、工厂涂装、发送出厂等。2)钢梁制造焊接环境相对湿度不宜高于80%。3)焊接环境温度：低合金高强度结构钢不得低于5℃，普通碳素结构钢不得低于0℃。4)主要杆件应在组装后2 4 h内焊接。5)钢梁出厂前必须进行试拼装，并应按设计和有关规范的要求验收。6)钢梁出厂前，安装企业应对钢梁质量和应交付的文件进行验收，确认合格。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]