[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149507":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149507,802,2,"多选题","钢梁制作与安装技术的要求包括()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","钢梁制造焊接应在室内进行，相对湿度不宜高于60％",false,{"key":16,"text":17,"correct":18},"B","主要杆件应在组装后24h内焊接",true,{"key":20,"text":21,"correct":18},"C","钢梁制造焊接采用普通碳素结构钢时，焊接环境温度不应低于0℃",{"key":23,"text":24,"correct":18},"D","钢梁制造焊接采用低合金高强度结构钢时，焊接环境温度不应低于5℃",{"key":26,"text":27,"correct":14},"E","当钢材表面有锈蚀、麻点或划痕等缺陷时，其深度不得大于该钢材厚度允许负偏差值的1／3","BCD","2020\u002F2019教材P82 （2）钢梁制作基本要求1）.钢梁制作的工艺流程：包括钢材矫正，放样画线，加工切割，再矫正、制孔，边缘加工、组装、焊接，构件变形矫正，摩擦面加工，试拼装、工厂涂装、发送出厂等。2）.钢梁制造焊接环境相对湿度不宜高于80%。3）.焊接环境温度：低合金高强度结构钢不得低于5℃，普通碳素结构钢不得低于0℃。4）.主要杆件应在组装后24h内焊接。5）.钢梁出厂前必须进行试拼装，并应按设计和有关规范的要求验收。6）.钢梁出厂前，安装企业应对钢梁质量和应交付的文件进行验收，确认合格。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]