[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149506":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149506,802,2,"多选题","预应力混凝土连续梁采用挂蓝悬臂浇筑工法施工，其中节段前端高程的确定是连续梁施工控制的关键。确定悬臂浇筑段前端底板标高应考虑的因素有（）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","挂篮前端的变形值",true,{"key":16,"text":17,"correct":14},"B","预拱度",{"key":19,"text":20,"correct":14},"C","已浇筑段的实际标高",{"key":22,"text":23,"correct":14},"D","温度影响",{"key":25,"text":26,"correct":27},"E","墩柱沉降",false,"ABCD","2020\u002F2019教材P80 预应力混凝土连续梁，悬臂浇筑段前端底板和桥面标高的确定是连续梁施工的关键问题之一，确定悬臂浇筑段前段标高时应考虑：(1)挂篮前端的垂直变形值；(2)预拱度设置；(3)施工中已浇段的实际标高；(4)温度影响。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]