[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149504":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149504,802,2,"多选题","悬臂浇筑法施工连续梁合龙段时，应符合的规定有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","合龙前，应在两端悬臂预加压重，直至施工完成后撤除",false,{"key":16,"text":17,"correct":18},"B","合龙前，应将合龙跨一侧桥墩的临时锚固放松",true,{"key":20,"text":21,"correct":18},"C","合龙段的混凝土强度提高一级的主要目的是尽早施加预应力",{"key":23,"text":24,"correct":18},"D","合龙段的长度可为2m",{"key":26,"text":27,"correct":14},"E","合龙段应在一天中气温最高时进行","BCD","2020\u002F2019教材P80 （3）连续梁（T构）的合龙、体系转换和支座反力调整应符合下列规定：1）合龙段的长度宜为2m；2）合龙前应观测气温变化与梁端高程及悬臂端间距的关系。3）合龙前应按设计规定，将两悬臂端合龙口予以临时连接，并将合龙跨一侧墩的临时锚固放松或改成活动支座；4）合龙前，在两端悬臂预加压重，并于浇筑混凝土过程中逐步撤除，以使悬臂端挠度保持稳定；5）合龙宜在一天中气温最低时进行；6）合龙段的混凝土强度宜提高一级，以尽早施加预应力；7）连续梁的梁跨体系转换，应在合龙段及全部纵向连续预应力筋张拉、压浆完成，并解除各墩临时固结后进行。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]