[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149501":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149501,802,2,"多选题","有关泥浆护壁冲击钻成孔叙述，正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","冲击钻开孔时，应低锤密击，反复冲击造壁，保持孔内泥浆面稳定",true,{"key":16,"text":17,"correct":18},"B","每钻进6～8m应验孔一次，在更换钻头前或容易缩孔处，均应验孔并应做记录",false,{"key":20,"text":21,"correct":14},"C","排渣过程中应及时补给泥浆",{"key":23,"text":24,"correct":14},"D","稳定性差的孔壁应采用泥浆循环或抽渣筒排渣",{"key":26,"text":27,"correct":14},"E","清孔后灌注混凝土之前的泥浆指标符合要求","ACDE","2020\u002F2019教材P71 3、冲击钻成孔：（1）冲击站开孔时，应低锤密击，反复冲击造壁，保持孔内泥浆面稳定。（2）应采取有效的技术措施防止扰动孔壁、塌孔、扩孔、卡钻和掉钻及泥浆流失等事故。（3）每钻进4-5m应验孔一次，在更换钻头前或容易缩孔处，均应验孔并应做记录。（4）排渣过程中应及时补给泥浆。（5）冲孔中遇到斜孔、梅花孔、塌孔等情况时，应采取措施后方可继续施工。（6）稳定性差的孔壁应采用泥浆循环或抽渣筒排渣，清孔后灌注混凝土之前的泥浆指标符合要求。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]