[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149500":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149500,802,2,"多选题","关于正、反循环钻孔施工的说法，正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","每钻进4～5m应验孔一次",false,{"key":16,"text":17,"correct":18},"B","设计未要求时摩擦型桩的沉渣厚度不应大于300mm",true,{"key":20,"text":21,"correct":18},"C","泥浆护壁成孔时根据泥浆补给情况控制钻进速度；保持钻机稳定",{"key":23,"text":24,"correct":18},"D","发生斜孔、塌孔和护筒周围冒浆、失稳等现象时，应先停钻",{"key":26,"text":27,"correct":18},"E","钻孔达到设计深度，灌注混凝土之前，孔底沉渣厚度应符合设计要求","BCDE","2020\u002F2019教材P71 2.正、反循环钻孔(1)泥浆护壁成孔时根据泥浆补给情况控制钻进速度；保持钻机稳定。(2)钻进过程中如发生斜孔、塌孔和护筒周围冒浆、失稳等现象时，应先停钻，待采取相应措施后再进行钻进。(3)钻孔达到设计深度，灌注混凝土之前，孔底沉渣厚度应符合设计要求。设计未要求时端承型桩的沉渣厚度不应大于100mm；摩擦型桩的沉渣厚度不应大于300mm。选项A是冲击钻施工的要求有人说A是正确的。答：注意A是冲击钻成孔的，不是正反循环钻孔的。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]