[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149495":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149495,802,2,"多选题","钢围堰浮运定位时，应对()时的稳定性进行验算。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","下沉",false,{"key":16,"text":17,"correct":18},"B","就位",true,{"key":20,"text":21,"correct":18},"C","浮运",{"key":23,"text":24,"correct":14},"D","吊装",{"key":26,"text":27,"correct":18},"E","着床","BCE","2020\u002F2019教材P69 八、（4）钢围堰浮运定位时，应对浮运、就位和灌水着床时的稳定性进行验算。尽量安排在能保证浮运顺利进行的低水位或水流平稳时进行，宜在白昼无风或小风时浮运。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]