[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149487":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149487,802,2,"多选题","后张法预应力管道安装要求中说法正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","金属管道应采用钢管连接",false,{"key":16,"text":17,"correct":18},"B","管道应采用定位钢筋牢固地固定于设计位置",true,{"key":20,"text":21,"correct":18},"C","管道检查合格后应及时封堵端面",{"key":23,"text":24,"correct":18},"D","管道应留压浆孔与溢浆孔",{"key":26,"text":27,"correct":14},"E","管道安装后，需在其附近进行焊接作业时，可不对管道采取保护措施","BCD","2020\u002F2019教材P55 本题考查的是预应力张拉施工。1）管道应采用定位钢筋牢固地定位于设计位置。2)金属管道结构应采用套管连接，选项A错误；3)管道应留压浆孔与溢浆孔。4)管道安装就位后应立即通孔检查，发现堵塞应及时疏通。管道经检查合格后应及时将其端面封堵，防止杂物进入。5）管道安装后，需在其附近进行焊接作业时，必须对管道采取保护措施，选项E错误。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]