[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149483":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149483,802,2,"多选题","后张有粘结预应力混凝土结构中，预应力筋的孔道应满足如下要求()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","足够的强度",true,{"key":16,"text":17,"correct":14},"B","足够的刚度",{"key":19,"text":20,"correct":21},"C","壁厚要求",false,{"key":23,"text":24,"correct":14},"D","不允许漏浆",{"key":26,"text":27,"correct":14},"E","能按要求传递粘结力","ABDE","2020\u002F2019教材P52 1)后张有粘结预应力混凝土结构中，预应力筋的孔道一般由浇筑在混凝土中的刚性或半刚性管道构成。一般工程可由钢管抽芯、胶管抽芯或金属伸缩套管抽芯预留孔道。浇筑在混凝土中的管道应具有足够强度和刚度，不允许有漏浆现象，且能按要求传递粘结力。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]