[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149478":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149478,802,2,"多选题","混凝土的()之和不应超过混凝土的初凝时间。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","运输时间",true,{"key":16,"text":17,"correct":14},"B","浇筑时间",{"key":19,"text":20,"correct":14},"C","间歇时间",{"key":22,"text":23,"correct":24},"D","拌合时间",false,{"key":26,"text":27,"correct":24},"E","出料时间","ABC","2020\u002F2019教材P51 2）混凝土运输、浇筑及间歇的全部时间不应超过混凝土的初凝时间。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]