[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149468":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149468,802,2,"多选题","计算梁的底模及拱架、支架的强度时，应采用的计算荷载有()等。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","倾倒混凝土时产生的水平冲击荷载",false,{"key":16,"text":17,"correct":18},"B","振捣混凝土时的荷载",true,{"key":20,"text":21,"correct":18},"C","施工活荷载",{"key":23,"text":24,"correct":18},"D","模板、拱架和支架自重",{"key":26,"text":27,"correct":18},"E","新浇筑混凝土自重","BCDE","2020\u002F2019教材P45 表1K412012:梁、板和拱的底模及支承板、拱架、支架等计算强度用①+②+③+④+⑦+⑧代号意思如下：①模板、拱架和支架自重；②新浇筑混凝土、钢筋混凝土或圬工、砌体的自重力；③施工人员及施工材料机具等行走运输或堆放的荷载；④振捣混凝土时的荷载；⑤新浇筑混凝土对侧面模板的压力；⑥倾倒混凝土时产生的水平向冲击荷载；⑦设于水中的支架所承受的水流压力、波浪力、流冰压力、船只及其他漂浮物的撞击力；⑧其他可能产生的荷载，如风雪荷载、冬期施工保温设施荷载等。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]