[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149467":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149467,802,2,"多选题","设计预应力混凝土结构模板时，应考虑施加预应力后()等。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","构件的上拱",true,{"key":16,"text":17,"correct":14},"B","支座螺栓位移",{"key":19,"text":20,"correct":21},"C","构件的非弹性变形",false,{"key":23,"text":24,"correct":14},"D","预埋件位移",{"key":26,"text":27,"correct":14},"E","构件的弹性压缩","ABDE","2020\u002F2019教材P45 7)设计预应力混凝土结构模板时，应考虑施加预应力后构件的弹性压缩、上拱及支座螺栓或预埋件的位移等。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]