[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149466":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149466,802,2,"多选题","模板、支架和拱架的设计中应根据()等因素设置施工预拱度。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","受载后基础的沉降",true,{"key":16,"text":17,"correct":14},"B","受载后杆件接头处的非弹性变形",{"key":19,"text":20,"correct":14},"C","受载后的弹性变形",{"key":22,"text":23,"correct":14},"D","结构预拱度的设计值",{"key":25,"text":26,"correct":27},"E","受载后的稳定性",false,"ABCD","2020\u002F2019教材P45 (6)模板、支架和拱架的设计中应设施工预拱度。施工预拱度应考虑下列因素：1)设计文件规定的结构预拱度；2)支架和拱架承受全部施工荷载引起的弹性变形；3)受载后由于杆件接头处的挤压和卸落设备压缩而产生的非弹性变形；4)支架、拱架基础受载后的沉降。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]