[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149454":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149454,802,2,"多选题","对沥青混凝土路面接缝的施工要求，下列说法正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","上下层的纵缝应错开100mm",false,{"key":16,"text":17,"correct":18},"B","相邻两幅的横向接缝应错位1m以上",true,{"key":20,"text":21,"correct":18},"C","高等级道路的表面层横向接缝应采用垂直的平接缝",{"key":23,"text":24,"correct":14},"D","采用梯队作业摊铺时应选用冷接缝",{"key":26,"text":27,"correct":18},"E","铺筑新混合料接头应使接槎软化","BCE","2020\u002F2019教材P32 （热接缝）或300-40Omm（冷接缝）以上。相邻两幅及上、下层的横向接缝均应错位1m以上。应采用3m直尺检查，确保平整度达到要求。2、采用梯队作业摊铺时应选用热接缝，将已铺部分留下100-00mm宽暂不碾压，作为后续部分的基准面，然后跨缝压实．如半幅施工采用冷接缝时，宜加设挡板或将先铺的沥青混合料刨出毛搓，涂刷粘层油后再铺新料，新料重叠在已铺层上50-100mn，软化下层后铲走，再进行跨缝压密挤紧。3、高等级道路的表面层横向接缝应采用垂直的平接缝，以下各层和其他等级的道路的各层可采用斜接缝。平接缝宜采用机械切割或人工刨除层厚不足部分，使工作缝成直角连接。清除切割时尚留下的泥水，干燥后涂刷粘层油，铺筑新混合料接头应使接搓软化，压路机先进行横向碾压，再纵向充分压实，连接平顺。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]