[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149439":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149439,802,2,"多选题","城镇道路基层施工时，石灰稳定土基层与水泥稳定土基层的运输与摊铺的规定有()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","拌成的稳定土类混合料应及时运送到铺筑现场",true,{"key":16,"text":17,"correct":14},"B","厂拌石灰土类混合料摊铺时路床应湿润",{"key":19,"text":20,"correct":14},"C","降雨时应停止施工，已摊铺的应尽快碾压密实",{"key":22,"text":23,"correct":24},"D","宜在秋末和气温较低季节施工，施工最低气温为-5℃",false,{"key":26,"text":27,"correct":14},"E","运输中应采取防止水分蒸发和防扬尘措施","ABCE","2020\u002F2019教材P25 一、石灰稳定土基层与水泥稳定土基层：（二）运输与摊铺：1、拌成的稳定土类混合料应及时运送到铺筑现场。水泥稳定土材料自搅拌至摊铺完成，不应超过3h。2、运输中应采取防止水分蒸发和防扬尘措施。3、宜在春末和气温较高季节施工，施工最低气温为5℃。4、厂拌石灰土类混合料摊铺时路床应湿润。5、雨期施工应防止石灰、水泥和混合料淋雨；降雨时应停止施工，已摊铺的应尽快碾压密实。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]