[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149438":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149438,802,2,"多选题","以下关于石灰稳定土基层运输与摊铺施工技术要点正确的是()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","雨期施工应防止混合料淋雨",true,{"key":16,"text":17,"correct":18},"B","应在第一次重冰冻到来之前一到一个半月内完成施工",false,{"key":20,"text":21,"correct":14},"C","降雨时应停止施工，已摊铺的应尽快碾压密实",{"key":23,"text":24,"correct":14},"D","运输中应采取防止水分蒸发措施",{"key":26,"text":27,"correct":14},"E","拌成的稳定土应及时运送到铺筑现场","ACDE","2020\u002F2019教材P25 （二）（1）拌成的稳定土类混合料应及时运送到铺筑现场。水泥稳定土材料自搅拌至摊铺完成，不应超过3h。（2）运输中应采取防止水分蒸发和防扬尘措施。（3）宜在春末和气温较高季节施工，施工最低气温为5°C。（5）雨期施工应防止石灰、水泥和混合料淋雨；降雨时应停止施工，已摊铺的应尽快碾压密实。选ACDE。“应在第一次冰冻到来之前1~1.5月以上完成施工”，B“一个半月内完成施工”,错。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]