[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149419":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149419,802,2,"多选题","路基施工时挖土路基的施工要点包括()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","根据测量中线和边桩开挖",true,{"key":16,"text":17,"correct":18},"B","压路机不小于8t级，碾压应自路两边向路中心进行",false,{"key":20,"text":21,"correct":14},"C","碾压时，应视土的干湿程度而采取洒水或换土、晾晒等措施",{"key":23,"text":24,"correct":18},"D","压路机不小于12t级，碾压应自路中心向两边进行",{"key":26,"text":27,"correct":14},"E","过街雨水支管沟槽及检查井周围应用石灰土或石灰粉煤灰砂砾填实","ACE","2020\u002F2019教材P17 （二）挖土路基：1、路基施工前，应将现况地面上积水排除、疏干，将树根坑、坟坑、井穴等部位进行技术处理。2、根据测量中线和边桩开挖。3、挖土时应自上向下分层开挖，严禁掏洞开挖。机械开挖时，必须避开构筑物、管线，在距管道边1m范围内应采用人工开挖；在距直埋缆线2m范围内必须采用人工开挖。挖方段不得超挖，应留有碾压到设计标高的压实量。4、压路机不小于12t级，碾压应自路两边向路中心进行，直至表面无明显轮迹为止。5、碾压时，应视土的干湿程度而采取洒水或换土、晾晒等措施。6、过街雨水支管沟槽及检查井周围应用石灰土或石灰粉煤灰砂砾填实。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]