[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149387":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149387,802,2,"多选题","钢管拱砼浇筑施工质量控制正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","砼泵送顺序宜先钢管后腹箱",true,{"key":16,"text":17,"correct":18},"B","质量检测以人工敲击为主，超声波为辅",false,{"key":20,"text":21,"correct":14},"C","应先泵入适量水泥浆再压注砼",{"key":23,"text":24,"correct":14},"D","压注砼完成后应关闭倒流截止阀",{"key":26,"text":27,"correct":18},"E","由一侧拱脚向拱顶连续压注完成后再压注另一侧","ACD","本题考查的是钢管混凝土浇筑施工质量检查与验收。钢管混凝土的质量检测应以超声波检测为主，人工敲击为辅；由两拱脚至拱顶对称均衡地连续压注一次完成。教材P367。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]