[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149376":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149376,802,2,"多选题","顶管作业质量控制表述正确的是（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","应遵循“勤测量、勤纠偏、微纠偏”的原则",true,{"key":16,"text":17,"correct":14},"B","进入接收工作井应提前进行顶管机位置和姿态测量",{"key":19,"text":20,"correct":14},"C","为防止管节飘移，宜将前3～5节管节与顶管机联成一体",{"key":22,"text":23,"correct":24},"D","采用敞口式顶管机，在允许超挖的地层正常顶进时，管下部135度范围内可以超挖15mm",false,{"key":26,"text":27,"correct":24},"E","钢管接口焊接完成后，进行防腐层补口施工后即可顶进","ABC","本题考查的是城市非开挖管道施工质量检查与验收。管下部135°范围内不得超挖；钢管接口焊接完成后，应进行防腐层补口施工，焊接及防腐层检验合格后方可顶进。教材P406。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]