[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149367":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149367,802,2,"多选题","热力管道直埋保温接头保温和密封规定正确的是（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","保温工艺应有合格的检验报告",true,{"key":16,"text":17,"correct":14},"B","接头钢管表面应干净、干燥",{"key":19,"text":20,"correct":14},"C","发泡后应及时密封发泡孔",{"key":22,"text":23,"correct":24},"D","接头外观可出现少量层间脱离现象",false,{"key":26,"text":27,"correct":24},"E","接头外护层安全完成后，必须进行50%的气密性检验并应合格","ABC","本题考查的是城市供热管网工程施工及验收的有关规定。选项D，接头外观不应出现过烧、鼓包、翘边、褶皱或层间脱离等缺陷。选项E，不是50%，是全部进行气密性试验。教材P470。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]