[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149337":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149337,802,2,"多选题","竣工图完成后，应经（ ）审核。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工单位项目负责人",false,{"key":16,"text":17,"correct":18},"B","施工单位项目技术负责人",true,{"key":20,"text":21,"correct":18},"C","监理单位总监理工程师",{"key":23,"text":24,"correct":14},"D","建设单位项目负责人",{"key":26,"text":27,"correct":14},"E","设计单位项目负责人","BC","竣工总图编绘完成后，应经施工单位项目技术负责人、监理单位总监理工程师审核、会签。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]