[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149334":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149334,802,2,"多选题","各级基坑均应量测项目包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","墙顶水平位移",true,{"key":16,"text":17,"correct":14},"B","墙顶竖向位移",{"key":19,"text":20,"correct":21},"C","围护墙深层水平位移",false,{"key":23,"text":24,"correct":21},"D","土体深层水平位移",{"key":26,"text":27,"correct":21},"E","墙体内力","AB","本题考查的是监控量测方法。一级、二级和三级基坑应测项目有（坡）顶水平位移、墙（坡）顶竖向位移、周围建（构）筑物裂缝、周围地下管线变形。教材P274。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]