[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149332":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149332,802,2,"多选题","下列关于HDPE 膜铺设施工要点说法正确是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","铺膜要考虑工作面地形情况，减少十字焊缝以及应力集中",true,{"key":16,"text":17,"correct":18},"B","填埋场HDPE 膜铺设总体顺序一般为“先场底后边坡”",false,{"key":20,"text":21,"correct":18},"C","在铺设时应将卷材自下而上滚铺",{"key":23,"text":24,"correct":14},"D","铺设边坡HDPE 膜时，为避免HDPE 膜被风吹起和被拉出周边锚固沟，所有外露的HDPE 膜边缘应及时用沙袋或者其他重物压上",{"key":26,"text":27,"correct":18},"E","冬期施工应做好防风与保温工作","AD","HDPE 膜铺设施工要点： 2）铺膜要考虑工作面地形情况，对于凹凸不平的部分和场地拐角部位需要详细计算，减少十字焊缝以及应力集中，A 对 4)为保证填埋场基底构建面不被雨水冲坏，填埋场HDPE 膜铺设总体顺序一般为“先边坡后场底”。在铺设时应将卷材自上而下滚铺，先边坡后场底，并确保贴铺平整，B、C 错 5）铺设边坡HDPE 膜时，为避免HDPE 膜被风吹起和被拉出周边锚固沟，所有外露的HDPE 膜边缘应及时用沙袋或者其他重物压上，D 对 7）根据焊接能力合理安排每天铺设HDPE 膜的数量，在恶劣天气来临前，减少展开HDPE 膜的数量，做到能焊多少铺多少。冬期严禁铺设，E 错",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]