[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149326":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149326,802,2,"多选题","管道焊接完毕后，焊缝需要进行100%无损探伤检测的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","干线管道与设备、管件连接处和折点处的焊缝",true,{"key":16,"text":17,"correct":18},"B","穿越铁路、高速公路的管道在铁路路基两侧各15m 范围内",false,{"key":20,"text":21,"correct":18},"C","穿越城市主要道路的不通行管沟在道路两侧各10m 范围内",{"key":23,"text":24,"correct":14},"D","不具备强度试验条件的管道焊缝",{"key":26,"text":27,"correct":14},"E","现场制作的各种承压设备和管件","ADE","穿越铁路、高速公路的管道在铁路路基两侧各10m 范围内、穿越城市主要道路的不通行管沟在道路两侧各5m 范围内，穿越江、河、湖等的管道在岸边各10m 的范围内的焊缝，应进行100%无损探伤检测。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]