[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149318":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149318,802,2,"多选题","压力管道试验准备工作的内容有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","试验管段所有敞口应封闭，不得有渗漏水现象",true,{"key":16,"text":17,"correct":14},"B","试验前应清除管内杂物",{"key":19,"text":20,"correct":14},"C","试验段内不得用闸阀做堵板",{"key":22,"text":23,"correct":24},"D","试验段内消火栓安装完毕",false,{"key":26,"text":27,"correct":14},"E","应做好水源引接、排水等疏导方案","ABCE","本题考查的是压力管道的水压试验。选项D，试验管段不得用闸阀做堵板，不得含有消火栓、水锤消除器、安全阀等附件。教材P206。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]