[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149313":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149313,802,2,"多选题","关于供热管道支、吊架安装的说法，错误的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","管道支架处不应有管道焊缝",false,{"key":16,"text":17,"correct":14},"B","活动支架的偏移方向、偏移量及导向性能应符合设计要求",{"key":19,"text":20,"correct":21},"C","调整支承面标高的垫板不得与钢结构焊接",true,{"key":23,"text":24,"correct":21},"D","有角向型补偿器的管段、固定支架不得与管道同时进行安装与固定",{"key":26,"text":27,"correct":21},"E","弹簧支、吊架的临时固定件应在试压前拆除","CDE","本题考查的是供热管道安装施工要求。选项C错误，管道支架支承面的标高可采用加设金属垫板的方式进行调整，垫板不得大于两层，垫板应与预埋铁件或钢结构进行焊接。选项D错误，有角向型、横向型补偿器的管段应与管道同时进行安装与固定。选项E错误，弹簧的临时固定件应在管道安装、试压、保温完毕后拆除。教材P219～220。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]