[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149303":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149303,802,2,"多选题","施工无抗浮结构设计的水池时，正确的降排水做法有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","选择可靠的降低地下水位方法",true,{"key":16,"text":17,"correct":14},"B","基坑受承压水影响时，应进行承压水降压计算",{"key":19,"text":20,"correct":21},"C","施工过程中间断降、排水",false,{"key":23,"text":24,"correct":14},"D","有备用降水机具",{"key":26,"text":27,"correct":14},"E","降排水应输送至抽水影响半径范围以外的河道或排水管道","ABDE","本题考查的是水池施工中的抗浮措施。在施工过程中不得间断降水排水。教材P199。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]