[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149296":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149296,802,2,"多选题","土压平衡盾构土仓压力维持采用（ ）方法控制。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","螺旋排土器转数",true,{"key":16,"text":17,"correct":14},"B","盾构千斤顶推进速度",{"key":19,"text":20,"correct":14},"C","螺旋排土器转数+盾构千斤顶推进速度",{"key":22,"text":23,"correct":24},"D","计算渣车搬运车台数",false,{"key":26,"text":27,"correct":24},"E","计算渣车搬运车重量","ABC","本题考查的是土压平衡盾构掘进。选项D、E属于排土量管理中容积管理法和重量管理法中的内容。教材P153。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]