[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149280":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149280,802,2,"多选题","隧道深孔注浆加固单孔结束标准正确的是（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","注浆压力逐步升高至设计终压，并继续注浆10min以上",true,{"key":16,"text":17,"correct":14},"B","检测孔钻取岩芯，浆液充填饱满",{"key":19,"text":20,"correct":14},"C","注浆结束时的进浆量小于20L\u002Fmin",{"key":22,"text":23,"correct":24},"D","注浆结束时的进浆量大于20L\u002Fmin",false,{"key":26,"text":27,"correct":24},"E","浆液有效注入范围大于设计值","ABC","本题考查的是深孔注浆加固技术。单孔注浆结束标准：（1）注浆压力逐步升高至设计终压，并继续注浆10min以上；（2）注浆结束时的进浆量小于20L\u002Fmin；（3）检测孔钻取岩芯，浆液充填饱满。教材P174。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]