[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149272":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149272,802,2,"多选题","预应力混凝土连续梁，悬臂浇筑段前端底板和桥面标高的确定是连续梁施工的关键问题之一，确定悬臂浇筑段前端标高时应考虑（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","挂篮前端的垂直变形值",true,{"key":16,"text":17,"correct":14},"B","预拱度设置",{"key":19,"text":20,"correct":14},"C","施工中已浇段的实际标高",{"key":22,"text":23,"correct":14},"D","温度影响",{"key":25,"text":26,"correct":27},"E","施工人员操作水平的影响",false,"ABCD","预应力混凝土连续梁，悬臂浇筑段前端底板和桥面标高的确定是连续梁施工的关键问题之一，考前黑钻押题，金考典软件考前更新，下载链接 www.jinkaodian.com确定悬臂浇筑段前端标高时应考虑：（1）挂篮前端的垂直变形值。（2）预拱度设置。（3）施工中已浇段的实际标高。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]