[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149270":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149270,802,2,"多选题","关于悬臂浇筑施工说法错误的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","合龙段的长度宜为2m",false,{"key":16,"text":17,"correct":18},"B","合龙宜在一天中气温较低时进行",true,{"key":20,"text":21,"correct":18},"C","合龙前，在两端悬臂预加压重，合龙前一次性撤除",{"key":23,"text":24,"correct":14},"D","合龙段的混凝土强度宜提高一级，以尽早施加预应力",{"key":26,"text":27,"correct":14},"E","梁跨体系转化时，支座反力的调整应以高程控制为主，反力作为校核","BC","合龙宜在一天中气温最低时进行，所以B 选项较低的说法错误；合龙前，在两端悬臂预加压重，并于浇筑混凝土过程中逐步撤除，以使悬臂端挠度保持稳定，所以C 选项一次性撤除的说法错误。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]