[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149265":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149265,802,2,"多选题","下列对钢绞线进场的检验要求，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","检查质量证明书和包装",true,{"key":16,"text":17,"correct":18},"B","分批检验，每批重量不大于65t",false,{"key":20,"text":21,"correct":14},"C","抽查3盘进行力学性能试验",{"key":23,"text":24,"correct":14},"D","检验有一项不合格则该盘报废",{"key":26,"text":27,"correct":18},"E","取双倍数量进行全部项的复验","ACD","本题考查的是预应力筋及管道。每批重量不大于60t；检验有一项不合格则不合格盘报废，并再从该批未试验过的钢绞线中取双倍试件进行该不合格项的复验，如仍有一项不合格，应逐盘检查。教材P52。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]