[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149250":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149250,802,2,"多选题","（2020年真题）在设置施工成本管理组织机构时，要考虑到市政公用工程施工项目具有（）等特点。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","多变性",true,{"key":16,"text":17,"correct":14},"B","阶段性",{"key":19,"text":20,"correct":14},"C","流动性",{"key":22,"text":23,"correct":24},"D","单件性",false,{"key":26,"text":27,"correct":24},"E","简单性","ABC","P299-303 市政公用工程施工项目具有多变性、流动性、阶段性等特点，这就要求成本管理工作和成本管理组织机构随之进行相应调整，以使组织机构适应施工项目的变化。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]