[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149237":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149237,802,2,"多选题","（2011 年真题）需专家论证的工程有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","5m 基坑工程",true,{"key":16,"text":17,"correct":14},"B","滑模",{"key":19,"text":20,"correct":21},"C","人工挖孔桩12m",false,{"key":23,"text":24,"correct":14},"D","顶管工程",{"key":26,"text":27,"correct":21},"E","250kN 常规起吊","ABD","开挖深度超过16m 的人工挖孔桩工程才需要专家论证，故C 错误。采用常规设备起重量30kN 及以上的起重设备安装工程才需要专家论证，故E 错误。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]