[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149235":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149235,802,2,"多选题","（2020年真题）关于因不可抗力导致相关费用调整的说法，正确的有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程本身的损害由发包人承担",true,{"key":16,"text":17,"correct":18},"B","承包人人员伤亡所产生的费用，由发包人承担",false,{"key":20,"text":21,"correct":14},"C","承包人的停工损失，由承包人承担",{"key":23,"text":24,"correct":14},"D","运至施工现场待安装设备的损害，由发包人承担",{"key":26,"text":27,"correct":14},"E","工程所需清理、修复费用，由发包人承担","ACDE","P289-292 因不可抗力事件导致的费用，发、承包双方应按以下原则分担并调整工程价款： (1)工程本身的损害、因工程损害导致第三方人员伤亡和财产损失以及运至施工现场用于施工的材料和待安装的设备的损害，由发包人承担。 (2)发包人、承包人人员伤亡由其所在单位负责，并承担相应费用。 (3)承包人施工机具设备的损坏及停工损失，由承包人承担。 (4)停工期间，承包人应发包人要求留在施工现场的必要的管理人员及保卫人员的费用，由发包人承担。 (5)工程所需清理、修复费用，由发包人承担。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]