[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149227":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149227,802,2,"多选题","（2011 年真题）GCL 铺设正确的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","每一工作面施工前均要对基底进行修正和检修",true,{"key":16,"text":17,"correct":14},"B","调整控制搭接范围250±50mm",{"key":19,"text":20,"correct":21},"C","采用上压下的十字搭接",false,{"key":23,"text":24,"correct":14},"D","当日铺设当日覆盖，雨雪停工",{"key":26,"text":27,"correct":14},"E","接口处撒膨润土密封","ABDE","根据填埋区基底设计坡向，GCL 垫的搭接尽量采用顺坡搭接，即采用上压下的搭接方式，注意避免出现十字搭接，而尽量采用品形分布，故C 错误。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]