[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149225":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149225,802,2,"多选题","（2017 年真题）关于生活垃圾填埋场HDPE 膜铺设的做法错误的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","总体施工顺序一般为“先边坡后场底”",false,{"key":16,"text":17,"correct":18},"B","冬期施工时应有防冻措施",true,{"key":20,"text":21,"correct":18},"C","铺设时应反复展开并拖动,以保证铺设平整",{"key":23,"text":24,"correct":14},"D","HDPE 膜施工完成后应立即转入下一工序,以形成对HDPE 膜的保护",{"key":26,"text":27,"correct":14},"E","应及时收集整理施工记录表","BC","B 项错在：HDPE 膜冬期严禁铺设。C 项错在：HDPE 膜铺设应一次展开到位，不宜展开后再拖动。D 项存在争议，最严谨的表述应为“防渗层验收合格后应及时进行下一工序的施工，以形成对防渗层的覆盖和保护”，D 项中的“施工完成”是否包含了“验收合格”、“立即”是否等同于“及时”存在争议；但基于多项选择题的判分规则，建议考试中慎选D 项。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]