[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149223":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149223,802,2,"多选题","（2020年真题）连续浇筑综合管廊混凝土时，为保证混凝土振捣密实，在（）部位周边应辅助人工插捣。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","预留孔",true,{"key":16,"text":17,"correct":14},"B","预埋件",{"key":19,"text":20,"correct":14},"C","止水带",{"key":22,"text":23,"correct":24},"D","沉降缝",false,{"key":26,"text":27,"correct":14},"E","预埋管","ABCE","P245-247 混凝土的浇筑应在模板和支架检验合格后进行。入模时应防止离析。连续浇筑时，每层浇筑高度应满足振捣密实的要求。预留孔、预埋管、预埋件及止水带等周边混凝土浇筑时，应辅助人工插捣。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]