[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149216":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149216,802,2,"多选题","（2019 年真题）关于供热管道安装前准备工作的说法，正确的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","管道安装前，应完成支、吊架的安装及防腐处理",true,{"key":16,"text":17,"correct":14},"B","管道的管径、壁厚和材质应符合设计要求，并经验收合格",{"key":19,"text":20,"correct":14},"C","管件支座和可预组织的部分宜在管道安装前完成",{"key":22,"text":23,"correct":24},"D","补偿器应在管道安装前先于管道连接",false,{"key":26,"text":27,"correct":14},"E","安装前应对中心线和支架高程进行复核","ABCE","教材原文“有补偿器装置的管段，补偿器安装前，管道和固定支架之间不得进行固定。”说明D项是错的，ABCE 为教材原文，根据多选题的答题规则也可以确定D 项是错的。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]