[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1149211":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1149211,802,2,"多选题","（2017 年真题）关于供热管网工程试运行的说法,错误的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程完工后即可进行试运行",true,{"key":16,"text":17,"correct":18},"B","试运行应按建设单位、设计单位认可的参数进行",false,{"key":20,"text":21,"correct":14},"C","试运行中严禁对紧件进行热拧紧",{"key":23,"text":24,"correct":18},"D","试运行中应重点检查支架的工作状况",{"key":26,"text":27,"correct":14},"E","试运行的时间应为连续运行48h","ACE","供热管网的试运行要求：（1）工程已经过有关各方预验收合格且热源已具备供热条件后，对热力系统应按建设单位、设计单位认可的参数进行试运行，试运行的时间应为连续运行72h。（2）试运行过程中应缓慢提高工作介质的温度，升温速度应控制在不大于10℃\u002Fh。在试运行过程中对紧固件的热拧紧，应在0.3MPa 压力以下进行。（3）试运行中应对管道及设备进行全面检查，特别要重点检查支架的工作状况。",{"id":6,"name":31,"category":32,"favorite":33},"一建市政公用工程实务","建筑工程",0]